Avoiding
Assumptions
Protecting
Client and Bidder in the Procurement Process With a Detailed
RFP
by Chuck Siebuhr
|
|
Professional
request for proposal (RFP) development can be, and usually
is, the most critical aspect of the entire procurement process.
Unfortunately, many do not recognize this fact until the project
starts failing, which is, of course, always too late. A carefully
conceived RFP is inarguably a recipe for protection. Detailed
research and documentation in the initial phases of a project
can and should assure protection from concept through completion
for the client and the bidder as well as any other involved
parties. In the final analysis, most projects that fail to
meet performance and/or cost expectations were usually undertaken
with superficial or certainly less than professional planning.
Under these circumstances, without a detailed and formal plan
of action including stringent checks and balances, failures
can and will occur. A seemingly small, often overlooked detail
can suddenly and unexpectedly produce a domino effect that
has disastrous and extremely visible results.
|
|
"...most
projects that fail to meet performance and/or cost expectations
were usually undertaken with superficial or certainly
less than professional planning..."
|
|
|
The various
reasons that projects fail are innumerable, but the root cause
is usually poor planning.
Commonly
encountered examples include RFPs and/or designs produced by
inexperienced project planners/engineers who are not conversant
with current industry standards. Significant investments are
expended on large projects and deserve the attention of professionals.
The larger and more complex the project, the higher the costs
and, therefore, the higher the risks. |
A typical and often mistaken assumption is that a professionally
developed RFP may consume too much time and expense to research
and prepare. History repeatedly proves this to be untrue. It
always costs more to correct problems and incur rework than
to do it right the first time. Remedial activities have far-reaching
implications, including not only the obvious cost of additional
labor and materials, but penalties associated with missed deadlines,
budget over-runs and potential contractual or legal liabilities.
In addition, client satisfaction is ultimately sacrificed in
the process, as well as any potential for future business relationships.
In many instances, failed projects have resulted in lengthy
court cases and substantial damages. |
|
Perspective
The RFP process should be analyzed and understood from the
perspective of both the client and originator (frequently
a consultant) and the bidder (usually the contractor). In
order to gain insight and a thorough understanding of the
complete end-to-end process, it is essential to analyze both
points of view. As a management tool, this knowledge can be
used to shape a mutually beneficial arrangement that strongly
resembles a partnership, rather than two entities with separate
agendas. These are, after all, business transactions, and
they should be fair and equitable for each entity, so both
parties achieve a win-win that is so often vocalized and not
so often realized. The advantages of forging such a working
relationship are invaluable over the long term.
|
|
Small Installations
Admittedly, it would not be necessary or feasible to create
a fully developed RFP for some smaller projects. Small, however,
is a relative term. A system of 500 work area outlets (WAOs)
may be large to some and small to others. As with any other
sound business decision, all facets should be carefully weighed
before committing or withholding resources. It is a judgment
call. Some smaller projects may be efficiently implemented
using a project mission statement or scope of work (SOW),
if sufficient detail is included and the document is incorporated
as part of the final contract. It should be noted that if
it is not clearly defined in detail, it will not be properly
executed. Leave no room for assumptions in either the SOW
or RFP. As the sayings go, "If it isn't in writing, it doesn't
exist," and "You get what you spec - not what you expect."
|
| "Some
client-generated RFPs are so loosely composed that
they could be labeled, "Victim waiting for predator."
Others are so tightly written and riddled with legalese
that they could be labeled, "We dare you to bid
this project." |
|
Dotting "i's" and
Crossing "t's"
The basic objective of the RFP is relatively straightforward:
to simplify, standardize and regiment the procurement
process. Unfortunately the path from concept to completion
is rarely as direct as the objective and can have serious
hidden penalties. It is not uncommon to have the bidder's
response forms and the entire RFP included as part of
the final contract. Therefore, every detail is important
and must be considered carefully before issuing the
RFP or submitting responses. If all of the "i's" and
"t's" are not addressed in this phase, they will most
likely be attended to and interpreted by an attorney
at a later date. The last line of defense in any contract
dispute, protest or challenge is the level of detail
included in these documents. The more definitive the
documentation, the better the defense for either group.
|
|
|
Details!
Some client-generated RFPs are so loosely composed that they
could be labeled, "Victim waiting for predator." Others are
so tightly written and riddled with legalese that they could
be labeled, "We dare you to bid this project." Neither of
these approaches is very effective as a project management
tool and both frequently lead to arbitration, whether informal
or formal. They certainly could not be used effectively as
guides for the implementation of large, complex projects.
A well-written professional RFP should be used as a guide
as well as a model and reference source for all facets of
the project. This type of RFP details the client's specific
performance requirements and clearly indicates what is expected
of the client and the bidder. Any area of the RFP that is
left vague and undefined will most certainly be misinterpreted
and laden with a$$umptions. The very foundation of any RFP
is anchored in detail.
|
|
Is All of this
Attention to Detail Really Necessary?
Yes, especially when selecting telecommunications systems,
whether PABX cabling, LAN-data backbone or horizontal cabling.
In larger projects, there is a tendency to focus on the big
decision (as in which manufacturer or system to buy). Meanwhile,
countless small decisions that should clearly define processes,
evaluations, account-abilities, schedules and technical qualifications
get overlooked.
|
Architecture
Architecture in the telecommunications industry usually
describes system architecture, more typically referred
to as hierarchies or topologies. There are certain similarities
between a building's architecture and a system's architecture,
inasmuch as no construction should begin without complete
detailed plans and schedules. And, nothing should proceed
without a solid, expertly designed and approved foundation.
Since we do not (yet) have telecommunications inspectors,
someone has to assume the responsibility of ensuring that
all codes, standards, ordinances and regulations or restrictions
are observed. These responsibilities may fall to the client
or consultant, engineer/planner, building owner or, in
some cases, the contractor/bidder, depending on how the
RFP is written. |
| "Designing
a telecommunications system to provision a campus
requires construction experience and a diverse technical
knowledge covering planning, design, media capabilities,
performance limitations and an almost limitless
variety of hardware and equipment." |
|
|
|
Preparing the RFP
As mentioned, responsibilities will vary from RFP to RFP.
Large corporations may be self-maintaining and have experienced
registered designers on staff who will prepare the design
and documentation. Other companies may elect to retain a consultant
and publish the RFP seeking a turnkey solution, while some
may contract out only the cabling portion or divide the implementation
into separate phases. Each situation and each site is unique
and must be treated as such if the desired results are to
be achieved.
Preparing
the RFP could be more correctly stated as "preparing to prepare
the RFP." A great deal of thought and planning must go into
the initial phase before making any committed decisions.
|
|
[top of page]
[next
page]
|
| |
Chuck
Siebuhr, RCDD, is senior technical editor for Cabling
Business Magazine and an instructor at Cabling Business
Institute. He has more than 30 years experience in the
telecommunications industry. Siebuhr is a founding member
of Association of Cabling Professionals (ACP), is a member
of BICSI, and is listed in National's Who's Who of Honored
Professionals and Executives, 1999-2000 edition. |
|
|
 |