|
Avoiding
Assumptions
Protecting
Client and Bidder in the Procurement Process With a Detailed
RFP
- Page 2
by Chuck Siebuhr
|
|
Site Survey
Large buildings and campus-type environments usually have
floor plans, layouts and site maps, even though they may not
be current. If a complete set of plans and maps does not exist,
the information must be gathered through a site survey. Whether
generated by the client for distribution with the RFP or performed
by prospective bidders, an accurate site survey must be conducted.
Even if there are existing plans and maps, the distances and
measurements must be verified.
|
|
Overview - Campus Environment
Designing a telecommunications system to provision a campus
requires construction experience and a diverse technical knowledge
covering planning, design, media capabilities, performance
limitations and an almost limitless variety of hardware and
equipment. For those who have not had an opportunity to implement
a project in a multibuilding campus environment, the following
is a brief overview of some of the many considerations that
must be addressed and definitively resolved early in the process.
The ultimate
design must ensure proper performance and establish a structured
distribution network that connects multiple detached buildings.
This is an infrastructure in which various media, including
copper, fiber and possibly microwave/wireless systems, transport
voice, high-speed data and/or video over a broad geographic
area. Generally referred to as a campus system (but not limited
to colleges or universities), it may include airports, hospitals,
military installations, industrial and manufacturing complexes
and residential and/or business parks. A campus outside plant
network includes all cable that extends outward from the main
cross-connect (MC), including support structures (conduit,
manholes, poles, etc.), necessary to connect all buildings
from the minimum point of entry (MPOE) protectors (demarc/demarcation
point).
|
|
The size and scope of work to be performed must be determined
in detail and well in advance of any formalized design. Typically,
the plan will have to pass through several levels of review,
analyses of cost vs. performance, and the reality or practicality
of proposed schedules for each phase. Resource allocations
must dovetail with prepared schedules and each step of the
process must receive advance approval from interdependent
principal parties involved in the effort. This phase is most
critical and assumptions must not be made. A typical fatal
assumption might be that the client's facility personnel will
actually have the trenches open when the shipment of conduit
arrives for placement and encasement.
Scheduling
and confirmation of schedules/resources are essential and
must be controlled closely. Also, there must be contingency
plans for each major undertaking. An unending number of factors
could jeopardize critical milestone dates, for example, unexpected
weather events, work stoppages, delayed permits, licensing,
inspections or any other external influence that perhaps could
not have been foreseen at the outset. This type of reasoning
is realistic and should emphasize the absolute necessity of
being as detail-oriented as possible when undertaking a complex
cabling project.
|
| "In
actuality, far more will be required of system
designers and project managers. Develop a
concise site plan that provides clear and
distinct physical details." |
|
Planning and
Design Procedures -Conceptual Phase
One of the important first steps is to determine
departmental end user requirements for each individual
entity. This usually requires a building-by-building
and floor-by-floor analysis. Consider present,
proposed and ultimate requirements. Make sure
the following areas are considered early in the
analysis:
MEDIA
UTILIZATION. Copper cable, fiber optic cable,
coaxial cable (not recommended), microwave or
other. Research the latest standards to ensure
that the selected media will satisfy the intent
of the final phase of the project and meet the
client's ultimate performance expectations.
|
|
|
MAIN DISTRIBUTION ROUTES/ CABLING. Originating
at the main cross-connect (MC) and typically consisting
of large pair-count cables (trunk) associated with underground
manhole systems and conduit routes.
|
|
|
BUILDING ENTRANCE CABLES. Typically, smaller cables
sized to serve a building (feeder) for its expected life cycle.
Includes hand holes, pullboxes or other support structures
necessary to facilitate final design.
PERIPHERAL
ISSUES. Environmental, EPA guidelines, restoration requirements,
etc. to include the following considerations:
- Pole
placement/replacement/disposal
- Manhole
environmentals and engineering
- OSHA/EPA
regulations, site-specific
- National
Electrical Code (NEC) and National Fire Protection Association
(NFPA) Code
- National
Electrical Safety Codes (NESC)
- Rights-of-way:
private, municipal, state and/or federal
- Tree
removals/landscape backfill, restoration
- Traffic
control, permits, fees, licensing, required inspections
- Property
boundaries and building ownership
- Aesthetics,
architectural constraints, etc.
- Any
legal implications that may be applicable on a case-by-case
basis.
|
|
Initial
Outline of Proposed Plan
With
the use of a site plan, lay out the campus interbuilding distribution
and entrance routes that will connect all buildings back to
the MC. Note on the plans the recommended type of direct buried,
underground or aerial cable plant required to support the
selected application and recommend the size or makeup (copper
and/or fiber) of entrance cable facilities.
Final
determination of construction will be based upon field review
of topography. With interbuilding routes and types of plant
and support systems tentatively identified, the sizing of
distribution and entrance cables may be determined. Compare
this actual derived information with the client's perceived
requirements. At this point, proposed design options are typically
accepted or amended as necessary.
The following
is a suggested format listing the major elements of a typical
campus telecommunications system. Remember, this is a brief
and summarized overview of what is required to execute an
implementation plan. In actuality, far more will be required
of system designers and project managers. Develop a concise
site plan that provides clear and distinct physical details.
After the major routes have been determined and approved,
cable-sizing requirements should start with the farthest location
from the MC and work backward, increasing pair counts or numbers
of required fiber strands along the way. This will later facilitate
the actual computation of the number, lengths and sizes of
support structures and conduits or duct bank requirements.
|
|
If Plans Do Not Exist
The planning effort, of course, mandates site plans of
existing and proposed buildings. Use architectural, electrical,
mechanical, other utilities, roadway plans, etc. If plans
do not exist, they must be created using exacting measurements,
acquired firsthand. Identify on the plan(s) all existing building
entrance routes by cable size and type of entry, underground
or aerial, copper or fiber. Clearly indicate the proposed
method of entering the structure, including feeder manholes,
pull-boxes and specify the location within the building (room
number, etc,). Clearly note all existing and proposed telecommunications
spaces/locations, including telco demarcation points or secondary
EFs (entrance facilities). It should be remembered that cables
leaving or entering unattached buildings require stringent
protection, bonding and grounding per NEC and TIA. Appropriate
equipment and exact locations should also be clearly noted
on plans.
Proposed
trunk (distribution) routes should be identified in a distinctive
manner, designating cable routes, size, type, pair counts
or fiber strands distributed at, or from, designated splice
points at respective manholes or other subterranean or aerial
structures. Additional information should specify individual
feeder routes to each building showing splice points and distribution
routes from feeder manholes or pull boxes. Also, indicate
which room, space or void will house each individual EF. Identify
each type of cable plant intended for immediate placement
or replacement and identify complements that are reserved
for future use. Plans should include all manholes, hand holes,
pullboxes, conduits, duct banks, buried cable trench routes,
aerial pole lines, etc. Each facility, cable type, complement,
support, housing, room, space and structure or component necessary
for the construction effort must be included on the plan(s).
Typically, multiple drawings either exist or must be prepared
to satisfy this requirement.
|
Attenuation
and/or Loop Limitations
Verify
and incorporate into the design all boundary locations
of overall campus facilities, including distance limitations,
copper and fiber attenuation, loss budget, PABX loop limits
and other pertinent physical and electrical characteristics.
These considerations may, and probably will, have a major
bearing on the overall design, especially on larger campuses
where greater distances are involved.
|
|
|
|
[top of page] [previous
page] [next
page]
|
|
 |