gharris@convergencecable.com

Avoiding Assumptions

Protecting Client and Bidder in the Procurement Process With a Detailed RFP
- Page 3

by Chuck Siebuhr

 

Field Review
After collecting verified field measurements and specific physical or topographical data, review the overall campus design with the client and/or other principal concerned parties, which may include city, municipal, state and federal authorities, for approval of proposed work to be performed. It should never be assumed that even the most detailed plan will be unanimously approved. It would be prudent to have at least an outline of a back-up plan, in the event that approval is not obtained.

Following formal approval by all principal parties, the next step in the process would be to finalize actual construction drawings and ensure that each project member receives a copy. This would include everyone from the project administrative staff to technicians, subcontractors and client personnel involved with the implementation effort. A complete set of drawings should be maintained in the project office and be used as a master plan. Accumulated information collected during field reviews or actual operations should be transferred to this plan immediately and communicated to all project personnel.

If this sounds like overkill, it isn't. Copies of plans are relatively inexpensive, while mistakes made because of lack of concise information are quite costly. Revisions, corrections, modifications and additions or deletions to the design must be communicated to all planholders as quickly as possible. Accurately detailed and uniformly used records are essential to the success of any project.


Plan Content

Proposed plans should include, but not be limited to, all arterial conduit, ducts, manholes, hand holes, pull boxes, pedestals, poles and splice points. Specify type, size and exact locations of all infrastructure components, supports, enclosures, protectors, type and size of copper or optical fiber cables, composition, and continuity from point of origination to destination. Note any special conditions such as poured or precast concrete, including type and placement of racking, manhole apparatus, pulling eyes and sumps.

CONDUIT. Specify and describe the type and size of conduit (minimum of four inches), schedule 40 PVC, concrete encasement (type), aluminum or steel. Specify backfill, restoration and overlay as required.

DISTRIBUTION AND/OR ENTRANCE. Conduit/cable routes/placement based on facility usage. Include spares for future use (minimum one 4-inch conduit).

INNER DUCT. Provision for fiber optic cable where applicable and note on plans.

BURIED CABLES. Not recommended, however if direct buried must be used, specify width and depth of trench, dirt, backfill, restoration and overlay. Recommend conduit placement for future usage (minimum one 4-inch conduit) wherever appropriate. Joint trench options with other utilities may be considered if applicable and conforming to NEC articles.

AERIAL. Recommend specific type/size of aerial cable and support strand, size, strength, placement techniques, pole and building attachment hardware, acceptable guying, span lengths, type (schedule) of poles, length (height), placement depth, etc. Specifications will depend on cable weight, prevailing weather, soil conditions, span lengths and loading, clearances, guying requirements and electrical separations as required by NEC codes, etc.


Joint Use (Pole) Options
Consider joint use as an alternative to new placement. Review pole use agreements, recurring costs, contract life cycle. Review rights of way and licensing by private, city, municipal, state or federal authorities or public utilities. Specify details of type, size and composition of cable, whether underground, buried or aerial, copper or fiber. Allow no substitutions to that which has been specified.


Media Requirements

Early identification of the following will be key to the final sizing effort for copper and optical fiber cable counts/complements:

  • Voice pairs needed per station
  • (WAO) per building and confirmed locations
  • Data pairs needed per station (WAO) per building and confirmed locations
  • Video pairs needed per building and confirmed locations
  • CATV needed per building (if applicable) and confirmed locations
  • Special circuits needed per building and confirmed locations
  • Provide appropriate entrance facilities for each media type (may require separate locations).
  • Identify type of LAN topology (star, bus, ring or hybrid). The type selected will affect cable sizes and lengths.
  • Eliminate all bridge tap and multiple pair assignments in any existing cables that may be scheduled for reuse.
  • Identify cable splice locations and pair counts that could prevent adequate sizing or dedication of pairs and/or cable homeruns into buildings or spaces.
Transmission Requirements
Voice provisioning may have different requirements (loop limitations) for 26, 24, 22 AWG, etc. For network (LAN/data) transmission rates, verify bandwidth, throughput, and research all physical or electrical characteristics prior to submitting an engineering plan. All media distance limitations must observe manufacturer's published design limits, as well as those prescribed in TIA standards.


Electrical Protection

The type of plant used in accordance with applicable NEC and municipal codes determines bonding and grounding requirements. For all telecommunications systems, TIA 607 should be the minimum acceptable method applied. Basically, this general design process of a campus telecommunications system is a concept that has been field and time-tested (and cost evaluated). As presented here, the overview can be shaped into a site-specific outline that is logical and adequate for presenting to the customer for review and approval. Once the initial concept is approved, a detailed scope-of-work document can be prepared and final negotiations may begin.

 

[top of page]      [previous page]